Changes made to dates of railroad work in Little Falls

Troy Shereck, Burlington Northern Santa Fe (BNSF) roadmaster informed the city of Little Falls that the following railroad crossings will be closed on the following dates:

• The schedule for work on the BNSF railroad crossing at Trunk Highway 27, Broadway Avenue West has changed. Work was originally set to be done Tuesday, May 21 – Thursday, May 23, and the road blocked off. However, that work has been shifted to the following week and the plans are to close Broadway West from May 28 – 30. to be blocked off from Tuesday, May 21 – Thursday, May 23,;

• The BNSF does know when the railroad crossing at Ninth Avenue Northwest will be blocked off. It was originally slated for May 28 – 30;

• The BNSF rail crossing at 123rd Street will be blocked off for one day only – Wednesday, May 29;  and

• The BNSF rail crossing at Eighth Avenue Southeast (Hilton Road) will tentatively blocked off Wednesday, June 5.

 

 